[ad_1]
- A £5 million-plus project to repair a broken flood wall in Matlock, Derbyshire
- The restoration of flood defenses by the Environment Agency will reach the halfway milestone at Christmas
- Flood defenses to better protect 50 homes and businesses from flooding
The project, which is being delivered in partnership with Derbyshire County Council and Derbyshire Dales District Council, follows the collapse of a privately-owned wall damaged by flooding in February this year. Restoring the city’s flood defenses will benefit 50 homes and businesses.
All sheet piles for the new flood wall have been installed except for the physical connection arrangement with the Matlock Bridge, which is a scheduled monument. Work has now been given permission from Historic England to proceed and will proceed under archaeological supervision.
Naomi Doughty, project manager at the Environment Agency, said:
Given how tough the Derbyshire Limestone has proven to be we have reached a significant milestone with the sheet piling. We are now working with Historic England to finalize the sheet piles next to Matlock Bridge due to the historical value of the bridge.
Weather permitting, we will begin piling the remaining sheet piles on Tuesday 6 December so that we can complete the bridge before Christmas Day.
This critical milestone in the construction program will provide a stable retaining wall upon which the flood wall can be built in the new year and ensure we quickly restore flood protection from the River Derwent for the town.
We would like to thank the local community for their continued support and understanding while building these essential flood defences, and apologize for the temporary disruption caused by the construction works.
Recent wet weather has caused some trees to fall into the River Derwent and pose a risk of blockage. The uprooted trees have been safely removed and a portion of the soft bank in front of the working platform has also been removed. This is being removed to prevent the risk of further bank collapse. Doing so would restore the original bank profile from the 1976 flood defense works and increase channel capacity.
Lifty McShifty, the giant 800-tonne crane that has graced the Matlock landscape since early August, is helping Environment Agency contractor Jackson Civil Engineering with its work to restore flood defences. It will be in place in the new year to enable cladding of sheet piles.
More information about the project can be found at: Matlock Flood Wall – Environment Agency – Citizen Space (environment-agency.gov.uk).
Background
The Environment Agency is working in partnership with Derbyshire County Council and Derbyshire Dales District Council to restore the river’s flood defenses after the February 2022 storms compromised the defenses when a wall collapsed behind businesses on Crown Square, Matlock, leaving Matlock vulnerable to river flooding. .
After the privately-owned wall collapsed, immediate repairs were carried out using a large crane on the A6 to place more than 50 bags of rock into the River Derwent. Further flood prevention work was carried out in April with an additional 100 2-tonne bags filled with rock being lifted into the River Derwent by a large crane located on the A6 to reduce erosion and limit damage sitting next to the Environment Agency flood wall. Collapsed private property wall.
The A6 between Matlock Bridge and the train station car park is now closed to all users (pedestrians, cyclists and vehicles) until new flood defenses are completed in 2023. Work on restoring flood defenses to meet this huge crane located on the A6. All northbound and southbound traffic will now be able to use Matlock Bridge.
[ad_2]
Source link