The Environment Agency is set to launch a £75 million project to protect homes and businesses from flooding in Kenway Island.
Most of Canvey Island is below the daily high-water level in the Thames Estuary. Tide defenses play an important role in reducing the risk of flooding to people, property and infrastructure on the island.
A 3 kilometer stretch of revetment of the island’s existing tidal flood defenses on the south shore between Thorney Bay and the island yacht club will be renewed. Sections of the existing revetment on the project area date back to the 1930s and need to be replaced.
Once completed, the island’s tidal defenses will continue to protect the 6,097 properties on the island for another 50 years. These works will also consider the effects of sea level rise due to climate change.
As well as refurbishing the existing tidal defences, additional enhancements will be made to the Canvey Island foreshore. This will include improved public access along the waterfront walkway.
New beach and foreshore steps as well as project information boards will be installed. The pathway surface along the landward side of the seawall between Thorney Bay and Chapman Sands will also be improved.
Flowering grass seed mix will be sown. This is to improve biodiversity on the preserve and rock pools will be created to promote habitat at selected locations along the coast.
The works are part of the Thames Estuary Asset Management (TEAM) 2100 programme. This is a 10-year capital investment program to refurbish and improve existing tidal flood defences. As the single largest flood risk management program in the UK, the TEAM 2100 program is refurbishing, repairing and replacing defenses where necessary across the Thames Estuary.

A concept sketch of what the proposed works to renew the erosion defenses on the seaward side of the existing tidal defenses will look like once completed
James Mason, Operations Manager at the Environment Agency, said:
The project is essential to managing flood risk for thousands of people, homes and businesses on Canvey Island.
Along the south coast the current juggernaut is starting to reach the end of its useful life. This investment in Canvey Island’s tidal defenses will ensure that they continue to benefit the community on Canvey Island until 2070.
We are already seeing the effects of climate change in the UK. That is why such plans are needed.
Everyone should know their flood risk and sign up for free flood alerts by visiting https://www.gov.uk/check-flood-risk or by calling the Floodline on 0345 988 1188. You can also follow @EnvAgency on Twitter for the latest information. Flood updates.
Contractors working on behalf of the Environment Agency will begin setting up the site from January, starting work on tide defenses from the end of March. The project is expected to take until summer 2025 to complete.
A public drop-in session will be held at Jimmy Mac’s Restaurant on 14 December 2022 from 11am to 2pm, before works start in the New Year. This session will provide an opportunity for the public and business owners to meet and speak with the project team.
the end
Notes to editors
- To find out more about the Canvey Island Southern shoreline revetment project, please visit https://consult.environment-agency.gov.uk/east-anglia-ce/canvey-southern-shoreline-project.
- Image Captions: Photo 1: Canvey seafront with revetment visible on the left. Photo 2: Concept sketch of what the proposed works to renew the erosion defenses on the seaward side of the existing tidal defenses will look like once completed.
- A record £5.2 billion investment will be made nationally between 2021-27, creating around 2,000 new flood and coastal risk management schemes to better protect thousands of properties across England.
- The schemes will help avoid £32 billion of widespread economic damage and reduce the national flood risk by 11%. It will reduce the risk of significant disruption to the daily lives of more than 4 million people due to possible future flooding.
Thames Estuary Asset Management 2100 Program (TEAM2100)
- The Thames Estuary Asset Management 2100 (TEAM 2100) program is a 10-year program to renew and improve existing tidal flood defences. It will run till March 2025.
- The program is refurbishing, repairing and replacing the most vulnerable assets in the Thames Estuary, as part of the Thames Estuary 2100 Plan.
- TEAM2100 is being distributed in partnership with Jacobs, Balfour Beatty and several other suppliers.
- For more information or to find out how you can get involved in Thames Estuary 2100, contact the team at thamesestuary2100@environment-agency.gov.uk.
Please contact the East Anglia Press Office (24 hours): 0800 917 9250
All Environment Agency news releases, both regional and national, can be found under Announcements at www.gov.uk/government/organisations/environment-agency.
Follow us on Twitter @EnvAgencyAnglia
[ad_2]
Source link